ORANGI PILOT PROJECT

RESEARCH AND TRAINING INSTITUTE  (OPP-RTI)

LOW COST HOUSING PROGRAMME 

 

B.  RESEARCH AND EXTENSION

8. OPP-RTI carried out research on the sociology, economics and technology of housing which showed that the building component manufacturing yard or thalla was the most important actor in the housing drama in Orangi.

9. Based on this research OPP-RTI gave credit and technical advice to thalla owners so that they could upgrade their products. Block making was mechanized.

10. New roofing systems that were cheap were introduced as an alternative of tin roofs. Theses could carry an additional floor.

 

Furthermore, research was carried out:

  1. to evolve standard construction design techniques.

  2. prepare standardized steel shuttering.

  3. write manuals and instruction sheets and prepare audio visual aids.

  4. to construct demonstration models.

 

This was further extended -

  1. to find thallawalas willing to participate in research and development (R & D).

  2. to train masons - teaching them improved design and construction techniques and the better use of tools.

  3. lending tool and shutterings.

  4. providing accurate plans and estimates.

Presently, the focus of the programme is training of masons, community architects and developing technical support institutions within the community, so that extension of the package of advice is more effective and independent.

 

The present package of advice is as follows:

  1. Appropriately designed in-situ foundation for a minimum ground + first floor construction

  2. 6" think load bearing walls of machine made blocks

  3. Batten/tile or T-girder/tile roofing and proper fixing

  4. Precast staircase

  5. Proper orientation and ventilation

  6. Proper construction techniques

This load bearing construction is 1/3rd the cost of the conventional Reinforced Concrete Construction.

An impact study was undertaken. Total 64 housing units constructed within the span of 5 years were surveyed. This study showed that:

  1. In 88 percent cases, foundation were made of proper ratio in situ concrete, however design dimensions were not adopted. Foundation bed was not laid, instead a straight footing of width 10" - 1'6" concrete was constructed.

  2. Damp proof course was not used.

  3. Walls were made of machine made blocks. The wall courses were proper, wall was in plumb and the wall joints were proper.

  4. In 80 percent cases, where need was to construct another storey, batton tiles were used. In 16 percent cases, tier girder tiles were used. In 100 percent cases, screeding was used, however, it was made stronger through reinforcement. The problem was provision of ring beam. In 50 percent cases, people had used the ring beam but the specifications had varied, effort had been made to make it unnecessarily strong so expensive.

  5. In 62 percent cases, cross ventilation had been adopted.

A second study comprising survey of 50 housing units was undertaken in Aug. 2002. Weaknesses and strengths as stated above were again observed.

In efforts to facilitate extension of techniques, leaflets based on the study were prepared and are being extended by the support institution TTRC to CBOs and masons.

 

11. Latest survey shows that 103 thallas have been upgraded, 200 masons trained. About 2,500 units per year benefit from the OPP-RTI technical research and extension.

12. Orangi masons were trained to use the new building products and were also given leaflets for assistance. Total 200 masons have been trained so far, of which 165 have been trained by an outshoot of the OPP-RTI: the Technical Training Resource Center (TTRC).

13. The OPP-RTI also provided guidance to the house owners by giving them layout plans for their houses and leaflets with guidelines on site supervision and estimates.

14. Houseowners thereby supervise their own construction.

15. The nature of housing in Orangi has improved as a result.

16. A house built using OPP-RTI technologies. Statistics are as follows:

Head............Cumulative (Jun 2007)

Units.................................311

Completed.......................265

Stopped............................. 42

In progress......................... 4

17. The youths of the communities are encouraged and trained as community architects.

18. The Technical Training and Resource Center (TTRC) has been set up spearheaded by a trained youth with two other former trainees and a teacher. Presently seven more Youths trained by TTRC are the additions to the team.Effort is also being made to replicate TTRC's work. Strengthening of another unit: Housing Resource Center (HRC) is being focused upon.

19. Now, the low cost housing activities including training, layout plans, design and estimate is being undertaken by TTRC with backup support from OPP-RTI. TTRC receives fees from houseowners and trainee youths. It has recently received empowerment fund from the Homeless International (HI) strengthening its institutional capacity.HI has provided additional funds of Rs.200,000 to support TTRC's replication.

 

    TTRC STATISTICS (As of Jun 2007)

    Plans and Estimates for total 355 units are complete.

    Supervision of total 132 projects are complete.

    Work in 105 school projects is complete.

    165 masons have been trained by the TTRC.

 

20. TTRC meeting with the community...

21. Research on new building components and other aspects of housing is carried out by the OPP-RTI. The picture shows an experiment being conducted for alternate roofing. A ferro cement roofing vault is being casted.

22. Yet another alternate for roofing is being made with tier girder and tiles.

 

Back<<                                                    >> Next

 

 

HOME

MAPS LOW COST SANITATION PROGRAM EDUCATION PROGRAM PUBLICATIONS